台积电据报准备再次上调 CoWoS 封装价格,涨幅最高达 20%,原因是 AI 封装需求超过供给。需求已从 GPU 扩展到服务器 CPU 和定制 ASIC,代工厂与封装厂预计涨价 10% 至 20%;设备交期从 3-6 个月拉长到 6-8 个月,更大尺寸封装还会降低单台设备每小时产出。台积电董事长魏哲家称,面积达最大可印刷芯片 5 倍的封装已量产且良率优异,9 倍和 14 倍方案在规划中。
TSMC is reportedly preparing another CoWoS price rise of up to 20% as AI packaging demand outruns supply.
CoWoS (Chip on Wafer on Substrate), joins an AI processor to its high-bandwidth memory on one densely wired base.
Demand has spread from GPUs to server CPUs and custom ASICs, so foundries and packagers expect 10% to 20% increases.
Supply can’t jump quickly, since equipment lead times stretched from 3-6 months to 6-8 months, and tool buyers no longer haggle.
Larger packages will deepen the squeeze, because they cut each tool’s hourly output, so even flat chip volumes need more machines.
They keep growing: TSMC chairman C.C. Wei says packages 5 times the largest printable chip are in mass production at excellent yields, with 9x and 14x planned.
来源:Rohan Paul · x.com