彭博报道称,开发商为美国数据中心宣布的自建电源(behind-the-meter)约90GW,但实际运行的只有约2GW,约占2%。
Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans:
developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far.
The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup.
AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year.
So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.